A water treatment facility called "Donets" in Kharkiv Oblast is planned for renovation.
The Kharkiv city council has transferred the project for the reconstruction of the "Donets" water supply complex to the Infrastructure Restoration and Development Service. The complex provides water to approximately 1.7 million consumers. The estimated cost of the work is 14.2 billion UAH, with 60 million UAH allocated this year for design and preparatory work.
The Kharkiv city council has transferred the project for the reconstruction of the "Donets" water supply complex to the Infrastructure Restoration and Development Service. The "Donets" complex provides water supply to approximately 1.7 million consumers.
The project involves the reconstruction of the water intake dam, the construction of a water intake facility from the Severskyi Donets River, main water pipelines for raw water, water treatment facilities, and pumping stations. The total length of the project is 44.39 km, and its capacity is 400,000 cubic meters of water per day.
The estimated cost of the work is 14.2 billion UAH. Head of the Restoration Service, Andriy Alexeev, noted that the full amount for construction is not currently being allocated, and the security situation must also be taken into account. 60 million UAH has been allocated for design and preparatory work this year.
The procurement and contract signing will be conducted through the Prozorro system. The "Donets" complex is located in the village of Kochtok, in the Chuguyiv district. It is a subsidiary of the "Kharkivvodokanal" enterprise and provides for the extraction, purification, and supply of drinking water to Kharkiv and nearby settlements.